Prime Minister Narendra Modi has been invited to flag off the muchawaited Hyderabad metro rail project in the city on November 28 this year . On Wednesday, Governor ESL Narasimhan, Telangana IT Minister K Taraka Rama Rao, Chief Secretary SP Singh and Municipal Secretary Naveen Mittal directed an assessment of Metro Rail Project.
They board the Metro Rail at SR Nagar Station and went till Miyapur. Hardly some days back, Prime Minister’s Office looked for a provide details regarding the advance of Hyderabad Metro Rail venture.
A Trial Run of Hyderabad Metro Rail was held from Begumpet to Ameerpet Today.
L&T Metro Rail Hyderabad (L&TMRH) has done the trial runs between Begumpet to S.R. Nagar via the Ameerpet interchange station are now ready to commence with the Government of India’s Chief Electrical Inspector D.V.S. Raju according sanction for energisation of Overhead Electric Traction System (OETS).
Trail runs were completed and safety certification obtained for Nagole to Begumpet and Miypur to S.R. Nagar. Ameerpet station has also got power supply connection last week and it has led to the illumination and functioning of lifts and escalators at the interchange station.
Telangana IT minister KTR educated Metro Rail will be prepared to work in an undeniable way by November fifteenth. Hyderabad Metro Rail Project have a between change intersection which is made by joining two unique corridors .
A man travelling out from Nagole to Miyapur ought to positively move to other Metro Train at Ameerpet. At once, Four Metro Trains can be worked. Upwards of 30,000 individuals could go in Metro Rail every day. By and large, Metro Train stops for only 20 Seconds at each station. The holding up time will be 2 minutes at Ameerpet Inter-Change Station.